Digital e-WZ in accordance with the PN-EN 206 standard and the clause regarding water addition on-site
How the digital e-WZ eliminates paper delivery slips and protects the concrete plant from unfounded complaints resulting from unauthorized water additions at the construction site.
PN-EN 206, Section 7.5, and the Unauthorized Addition of Water at the Construction Site
One of the most common disputes between the concrete plant, the site manager, and the flooring contractor concerns the consistency of the concrete mix when the concrete mixer truck arrives at the construction site. Sometimes, in an effort to make it easier to spread the concrete or speed up the pumping process, contractors demand that the mixer truck driver: *“Add about a hundred liters of water from the washdown system—it’s too thick!”*.
From a technical and legal standpoint, this is a cardinal error: - According to the PN-EN 206 standard (section 7.5): *“Under no circumstances is the addition of water or admixtures permitted during delivery, unless it is carried out under the supervision and responsibility of the manufacturer or when the specification provides for an appropriate procedure.”* - Increasing the water-to-binder ratio ($w/c$) by as little as 0.05 drastically lowers the compressive strength class (by as much as 20–25%), increases shrinkage, causes a network of cracks, and compromises the designed watertightness ($W$).
Legal Consequences of the Water-Addition Clause: A Precise Definition of Liability
Many myths have arisen surrounding the water-addition clause. It is worth clarifying the legal consequences in light of the provisions of the Civil Code:
Legal assessment of liability and warranty:
Signing a clause regarding water addition at the construction site does not automatically and completely invalidate the contract or extinguish all warranty rights in matters unrelated to consistency (e.g., defects in the aggregate used).
However: The submission by the recipient (construction manager/foreman) of a written or digital statement regarding the addition of a specified number of liters of water at their own request results in the transfer of liability for strength-related defects directly to the client. In the event of ceiling cracks or failure to meet the strength class in 28-day sample tests, the concrete plant has solid, indisputable proof that it delivered a product compliant with the standard, and that any modification was made at the customer’s request.
The Advantages of the Digital e-WZ on the Driver’s Smartphone or Tablet:
- No possibility of retroactive manipulation: Paper delivery notes (WZ) can get lost, get soaked on the construction site, or be signed illegibly by unauthorized persons.
- Accurate recording of parameters: The digital e-WZ system on the SENTBeton platform requires the driver to record the exact time of arrival, the start of unloading, and the precise number of liters of water added (with a signature lock that prevents entry without the recipient’s name).
- Electronic biometric signature: The recipient’s signature, provided on-screen with a GPS geolocation and timestamp, is immediately sent to the plant’s ERP system and is visible to the dispatcher.